Village Green Pavilion

Project updates

May 10, 2024

The project is complete with the exception of some punch list work.  The Grand Opening of the facility is currently rescheduled for May 18, 2024. 

March 28, 2024

This project carries over from 2023 as planned and included new water main and service lines, new storm sewer, and roadway reconstruction.  The section from West Ave. to Holman View was completed last year (except the surface course of asphalt) and the section from West Ave. to Springfield Pike will be completed this summer (while school is not in session). 

November 1, 2023

The south end of the project is substantially complete and the north end is scheduled for completion by November 20, 2023. The main work remaining consists of the pavilion roof (both top and bottom sides), sod for the Event Lawn, and some additional sidewalk work around the perimeter.

August 4, 2023

The pavilion work has begun with electrical rough-in work, block wall beginning, etc.  The seat wall, storm sewer, and other improvements on the south end are underway.  Work will continue through the summer with an anticipated completion date of October 1.

July 9, 2023

The foundations for the pavilion were poured this week and the (2) trees transplanted at Crescent Park. Work will continue through the summer with an anticipated completion date of October 1.

June 9, 2023

Alpha Construction has completed the demolition work and will begin underground utility work next week. The project is scheduled for completion October 1, 2023.

May 22, 2023

Alpha Construction will begin work the week of June 29. The project is scheduled for completion October 1, 2023.

April 17, 2023

Bids were opened on April 13, 2023, with Alpha Construction as the low bid at approximately $1.4 million. A resolution to award a contract is on the agenda for the April 17, 2023, City Council meeting.